Change order upsizes water main; Logistics Parkway cost now about $5.3 million
Summary
Staff said field conditions required upsizing a water main and relocating backflow devices on Logistics Parkway. The change order was stated as $1,669,978 and will bring total project cost to about $5.3 million; utility costs will be accounted for by transferring funds between utility and transportation funds.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Todd briefed the commission on a change order for the Logistics Parkway project. During construction staff found an existing 16-inch water main that required upsizing and the relocation of several backflow devices serving adjacent industrial businesses.
Todd said the change-order amount is $1,669,978 (the figure was clarified during the discussion) and will increase the overall project cost to about $5.3 million. He said the extra expense will be covered by utility costs being transferred from utility operations into the transportation fund that finances the project.
Staff described these as field-driven utility adjustments that were necessary to align the project with existing infrastructure and future operational needs. The project remains on schedule, and staff expects to begin closeout work within the next six months.