School construction nears completion; committee approves invoices, change orders and conduit groundwork to avoid future digging

Town of Cheshire school project committee · April 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Committee heard construction progress updates for Norton and Barnum, approved multiple vendor invoices and PCOs, and authorized trenching and conduit work (not-to-exceed amounts) to preserve new finishes if a separate district solar project proceeds.

The Town of Cheshire project committee received progress reports and voted on several financial and construction items as school construction nears substantial completion.

Project staff showed extensive photos of Barnum and Norton schools, described progress on windows, brick, canopies, playgrounds and interior finishes, and said permanent power and transformer work with Eversource is scheduled in the coming weeks. Staff gave a conservative target of early May for permanent power and a June 1 ‘‘drop-dead’’ date for remaining electrical work if delays occur.

In financial business, the committee approved multiple invoices by unanimous vote, including a construction-manager invoice for…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans