VMRC approves Robins Maritime mooring dolphins and steel pile conditions; bulkhead infill approved with conditions
Summary
VMRC approved Robins Maritime’s request for 13 mooring dolphins and — after debate — approved the applicant’s proposed 10‑ft bulkhead infill with VIMS pile‑driving conditions and city requirements to remove derelict barges.
Get email alerts on the Permitting Bulkhead topic
No spam. Unsubscribe anytime.
Robins Maritime sought authorization on April 21 to construct a 66‑ft steel bulkhead (channelward up to 10 ft) and to install 13 mooring dolphins on a Pearl Street property in Norfolk. VMRC staff recommended denying the 10‑ft fill because it would permanently convert roughly 660 square feet of subaqueous bottom to fill, and instead suggested an open‑pile wharf or a 2‑ft encroachment as alternatives. Staff did not object to the proposed mooring dolphins, recommending standard steel‑pile and timing conditions from VIMS.
Applicant representatives and a company president explained the operational safety need: a short extension of the bulkhead would allow a structural crane pad to lift small service tugs and other vessels safely, shortening crane reach and reducing risk of dropped loads and injuries. They showed draft crane capacity charts and said derelict barges on site had been removed at city direction.
Commissioners debated the trade‑off between habitat loss and workplace safety; asked whether a wharf or smaller encroachment could meet operational needs; and requested VIMS‑recommended mitigation for pile driving. After discussion, commissioners approved the project as submitted with VIMS pile‑driving and timing conditions and city‑requested removal of derelict structures, citing the need to balance navigation safety and local economic activity. Staff will include the standard environmental conditions in the permit package.