Summary
The board adopted ordinance 2026-4 (amending 2019-9) to set a schedule of fees for work in county right-of-way, waived the second reading, and directed collections to the Motor Vehicle Highway (MVH) fund for future appropriation.
Get email alerts on the Finance topic
No spam. Unsubscribe anytime.
Morgan County commissioners voted on April 20 to adopt ordinance 2026-4, updating the county’s fee schedule for work performed in the public right-of-way. The board voted to waive the second reading and adopt the ordinance by voice vote.
County staff said the fees are modeled on nearby Hendricks County’s schedule after reviewing fee structures from several neighboring jurisdictions. ‘‘We went with what Hendricks County charges…because they were close by and made sense for our parameters,’’ a county official said.
Staff explained that fee revenue will be collected into the Motor Vehicle Highway (MVH) fund. "Any of the fees we collect goes to MVH funds so we can use it to put back in and take care of the roads and infrastructure," a commissioner said; staff noted that using those funds for projects requires a separate appropriation.
The ordinance adds a fee schedule to the existing permit application process on the county website and may require bonds for larger projects, as allowed under the statute being amended. Commissioners agreed to waive the second reading so the fee schedule could take effect without delay; an effective date was not specified during the discussion.