Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Site Selection topic
No spam. Unsubscribe anytime.
Committee narrows elementary-school site study to Robinson and Abbott after desk-top review
Summary
Consultants reported that of six town-owned parcels reviewed, two — the Robinson School and Abbott School sites — will be carried forward into preliminary studies; other parcels face probable Article 97 protections, water-supply designations, wetlands or steep slopes. Costs for Abbott may rise if an on-site wastewater plant is required.
Get email alerts on the Site Selection topic
No spam. Unsubscribe anytime.
Consultants presented desk-top analyses April 14 to the Robinson School Building Committee and recommended carrying two primary site options — the Robinson School parcel and the Abbott School parcel — into the Preliminary Study Report (PSR) rather than the other town-owned candidates.
At the meeting, the project consultant summarized findings of the six-parcel review, noting that Two Farmer Way (the Ruck fields) and Jack Walsh Fields are “highly likely to be protected under Article 97,” a state law that restricts converting recreational land to other uses without legislative approval. The consultant said 17 Main Street and an adjacent parcel are designated water-supply land and “would severely limit any other use.” Jenny, the presenter, said the Robinson parcel has wetlands, priority habitat and a culverted perennial stream with regulatory setbacks and that “we've identified about five and a half acres of buildable land.”
The committee discussed how the 5.5-acre estimate applies to design scenarios. The consultant clarified that the figure excludes the existing school footprint and that a two-story replacement on the identified footprint could accommodate roughly 700 students, but that doing so would require planning for swing space during construction.
By contrast, the Abbott parcel was described as having no identified wetlands or priority-habitat constraints and about 11.75 acres when combining fields and parking. A committee member who had consulted with Water Superintendent Mark Warren warned that selecting Abbott could require “building a brand new wastewater treatment plant on site” because the existing system there is at capacity; the Robinson school currently feeds an off-site plant reported to be operating at roughly one-third of capacity. The consultant said cost estimates in planning scenarios will explicitly factor in wastewater and other site-dependent infrastructure needs.
Committee members asked consultants to verify deed stipulations and ownership details before eliminating sites. The land-use department will prioritize checking Two Farmer Way deeds this week, and consultants said they will review deed language for Abbott and Robinson as part of the next steps.
The committee agreed with the consultant recommendation to continue carrying multiple site options into PSR and to select a preferred site once enrollment figures and additional studies (geotechnical borings, surveys, traffic) provide clearer constraints and cost implications. Geotech borings were tentatively scheduled for April 27–28, and existing-conditions and traffic findings are slated to be reported back to the committee in May.
The committee did not take a formal site-selection vote during the meeting; members asked that findings, presentation slides, and follow-up materials be posted to the project website and included in town newsletters for public transparency.

