Board approves Hansen task‑order amendments after staff negotiation, commissioners demand tighter controls
Summary
The Authority approved $315,000 in negotiated task‑order amendments with on‑call engineer Hansen Professional Services for completed and ongoing projects, while commissioners criticized the after‑the‑fact presentation and asked for improved documentation and project controls.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Staff asked the board to approve task‑order amendments with Hansen Professional Services covering four projects: perimeter roads, parking lot, facilities improvements and fuel‑farm work. Deputy Executive Director Justin Lobb said staff negotiated Hansen’s original request down to about $315,000 and that the amendments include a release settling costs on projects that had unusual circumstances (extended permitting, contractor insolvency, added time).
Several commissioners expressed concern that substantial work or change orders occurred before board approval. Vice Chair Crease called the situation "deeply troubling" and requested assurance the negotiated amount represents fair value; Lobb said staff performed a line‑by‑line review and is implementing internal controls to avoid recurrence. Hansen’s aviation services manager Todd Merihue attended and said the firm had been "overzealous" in driving projects to completion and agreed to improve documentation and coordination.
The board voted to approve the negotiated amendments but asked staff to return with strengthened contractual timelines and clearer processes for notifying the board when task orders exceed scope. "We need better checks and balances so this doesn’t happen again," a commissioner said during debate.