Owasso approves $864,750 award for Hell Acres water‑line replacement and CDBG budget amendment

Owasso City Council / Owasso Public Works Authority / Owasso Public Golf Authority · May 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a capital improvement grants budget amendment to record $322,603.96 in CDBG revenues and awarded the Hell Acres Phase 3 water‑line replacement contract for $864,750 to the low bidder.

Council approved a budget amendment to bring federal Community Development Block Grant (CDBG) revenues into the capital improvements grants fund and awarded the Hell Acres Phase 3 water‑line replacement contract to the low bidder, staff said.

Staff explained the project replaces aging 6‑ and 8‑inch water lines and presented bid results. Creek Construction submitted the lowest qualified base bid and bids for alternates; staff recommended awarding the base bid plus alternates for a total award of $864,750. "The low bidder was below the engineer's estimate," staff said. To record grant funding, staff requested an amendment to increase estimated revenues and appropriations in the capital improvement grants fund by $322,603.96 to incorporate the CDBG award.

Council approved the budget amendment and the award and authorized execution of necessary documents. Staff said using a phased approach and combining grant cycles reduced mobilization costs and that funding would include CDBG resources and OPWA match amounts.