Owasso public works reports progress on Garnett widening, new facility occupancy and US‑169 work
Summary
Public works staff reported the Garnett widening has underground infrastructure roughly 70% complete, the new public works facility is nearing occupancy and US‑169 improvements remain on schedule for August 2026; staff also discussed right-of-way and utility-relocation timing for multiple projects.
The Owasso City Council heard a detailed monthly project-status report from Roger Stevens covering multiple road and facility projects.
Stevens said the Garnett widening (106th to 116th Street North) has most underground work underway — water and stormwater installation are about 70% complete and sanitary sewer installation is complete — and that paving will follow once underground work finishes. He said additional resurfacing and mill-and-overlay…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat