Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
County hears details on Constableville West Main Complete Streets project; committee forwards contract award to full board
Summary
BCA engineers described a Complete Streets reconstruction of West Main (CR‑52) in Constableville, estimating total project costs around $2.5 million and recommending award to the lowest responsive bidder; the committee forwarded a draft resolution to award a contract not to exceed $1,983,120 to the full board contingent on insurance, bonding and compliance documents.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
BCA Architects & Engineers and county planning staff presented the West Main Street Complete Streets project in Constableville, outlining a full‑depth reconstruction of about 1,900 feet on County Route 52 with new curbs, sidewalks, a stormwater system, bio‑retention, stamped concrete snow storage, on‑street parking and coordination with a village water main replacement.
"The total project cost right now as we understand it is looking like 2.5 million dollars," BCA staff said, describing the engineering budget, recommended contingencies and anticipated CHIPS reimbursement eligibility for portions of the work. Bids opened April 23, and the consulting engineer completed standard bid‑qualification checks.
County planning staff and BCA recommended moving forward with award of the construction contract. The draft resolution distributed to the committee authorized awarding the West Main Street contract in Constableville to the lowest responsive bidder "in an amount not to exceed $1,983,120," subject to required insurance, bonding and compliance documentation.
Committee members questioned construction timing and operations, including contractor mobilization and coordination with the village water project. BCA said they expect a July mobilization with substantial completion by the following November for major elements and restoration into spring 2027, and that the village's water work would begin slightly earlier to avoid rework.
The committee voted to forward the draft resolution authorizing the contract award to the full board for action. Members also approved a separate draft resolution to amend the county's professional services agreement with BCA to add resident project representation, right‑of‑way assistance and permitting support at an additional cost not to exceed $133,000, bringing total contract value to $378,000.
The record includes inconsistent spellings for the apparent low bidder in presentation materials ("Powless Contracting") and the draft resolution language ("Powis Contracting Incorporated"); county staff indicated the contract award is contingent on final documentation and compliance checks before execution.

