Planning Commission approves Genesis Credit Union site plan with fire-marshall condition
Summary
The Planning Commission approved a site plan April 29 to demolish a closed Arby's and build a Genesis Credit Union branch at 29515 Southfield Road, subject to planner and fire marshal sign-off on drive-through canopy clearance and standard conditions for landscaping, lighting, and security.
Get email alerts on the Genesis Credit Union topic
No spam. Unsubscribe anytime.
The City of Southfield Planning Commission on April 29 granted final approval to a site plan to demolish the vacant Arby's at 29515 Southfield Road and construct a new Genesis Credit Union branch, subject to conditions including fire-marshal clearance for the drive-through canopy and implementation of Police Department crime-prevention recommendations.
Project details: The plan calls for a single-story bank building with a three-lane drive-through (one lane serving an internal ATM), a canopy for drive-through lanes, landscape buffers to adjacent residential zones, a detention basin to improve stormwater performance and a reduction of impervious area compared with the former restaurant site. The project retains an existing six-foot screening wall at the rear, adds ornamental fencing and brick piers near pedestrian entrances, and includes a public-art fund contribution if the project cost exceeds $1 million.
Code and safety questions: During study-session follow-up, a planner noted National Fire Code guidance for canopy clearance (13.5 ft) and said the fire marshal reviewed a bypass/outer lane arrangement and indicated the proposed configuration could be acceptable if accessible. Staff made the canopy clearance a condition of approval: the planner and fire marshal must sign off before final permit issuance.
Outcome: Planning staff recommended approval of PSP26-00005 conditioned on development consistent with revised plans dated April 17, 2026, compliance with police crime-prevention recommendations, and continuous compliance with all applicable codes and permits. Commissioner Bernudi moved for approval, supported by Commissioner Martin; the commission voted to approve the site plan with the fire-marshall/planner condition.
Community context: Genesis Credit Union representatives presented their institution's nonprofit, member-owned structure and described outreach activities; commissioners praised the landscaping, reduced impervious surface and updated stormwater design as improvements over the previous development.
Next steps: With commission approval, the applicant proceeds with building-permit submittals and must obtain planner/fire-marshall sign-off on canopy clearance before final permits are issued.