Council questions $4.75 million low bid and funding plan for sewer upgrades
Summary
Council member 'Xavier' asked for a breakdown of a roughly $4,748,000 low bid on contract B3 and whether sewer work would be funded from sewer funds or lease revenue bonds; staff said allocations have not yet been determined and that the project includes upgrades on Monte Vista Avenue and Arrow Highway.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council members pressed staff for detail on a public-works contract described as item B3 during the consent-calendar discussion.
A council member identified in the transcript as Xavier asked how much of the previously estimated $6.5 million would be paid from sewer funds versus lease revenue bonds and what sewer upgrades the contract would include. City staff responded that the low bid is "approximately $4,748,000," that lease revenue bonds have "about $23 million" remaining, and that allocations among funding sources had not yet been determined. Staff said the contract includes upgrades to the sewer line on Monte Vista Avenue (from Arrow Highway north to Rickton) and work on Arrow Highway east of Monte Vista to address capacity and anticipated demand.
Staff repeatedly stated the precise funding distribution had not been finalized: "we have not allocated that out yet. We will have to determine what the distributions will be as we go forward with designing or completing the project," a staff speaker said in the meeting record.
What happens next: Staff said the low bid would be brought back to the council for consideration at a future meeting once allocations and design details are finalized.
Ending: The consent-calendar process continued while council members requested further budget breakdowns; no contract award or final allocation decision was made in the public portion of this meeting.