Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District hears capital-project update: asbestos abatement, auditorium and classroom renovations scheduled this summer
Summary
Palumbo Group presented phase-two and phase-three summer construction plans for the South Orangetown district, including asbestos remediation and targeted substantial-completion dates in late August; board members confirmed walk-throughs and coordination with school schedules.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Mike De Vogel of Palumbo Group gave the board a detailed construction and capital-project update, outlining the district's summer schedule for phased work and asbestos remediation.
Palumbo Group's presentation said the district is closing out bond phase one at four schools and moving into phase two, which includes renovation of the 300s wing and a fitness-center upgrade; asbestos remediation is scheduled to begin at the close of the school year with substantial completion for phase two set for Aug. 24. The auditorium (bond phase 2A) will see asbestos abatement beginning June 30 and field work starting June 26, the presenter said. Phase three covers middle-school classroom renovations, practice-field work, a new walking path and high-school administrative suite upgrades, with asbestos remediation timelines and a targeted Aug. 25 completion for phase three items.
The presenter listed typical scope items for classroom and auditorium work: abatement, HVAC and lighting upgrades, stage renovation, ADA seating improvements, casework replacement and finish upgrades. He described a preseason of documentation, temporary protection plans, coordination with building staff for packing out students, and contractor mobilization timed to the end of the school year.
Board members asked for and were told there would be summer and end-of-summer walk-throughs. Administrators explained they are coordinating schedules to allow summer athletics camps and district summer programming to proceed while maximizing construction progress.
No action items were required at the meeting; the presentation was informational and the contractor said he would return for walk-throughs and further updates. Board members thanked the presenter and reiterated their interest in close coordination to avoid impacts on summer programming.
The district previously noted it will continue practicing safety drills and rotate such drills across schools; the presentation emphasized asbestos removal will be staged to minimize disruption, starting with the most affected areas and proceeding through demo and renovation as school buildings empty for summer.

