Committee approves Hokum Woods Parkway stormwater pipelining task order with contingency authorization
Summary
The committee approved a task order to rehabilitate corrugated metal pipe on Hokum Woods Parkway, recommending the low bidder (Utility Asset Management) with staff-presented total authorization of $97,245 to include contingency; council discussed materials and methods before unanimous approval.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Mr. Watson described the Hokum Woods Parkway pipelining project as the second-ranked stormwater CIP item and explained the scope: roughly 130 feet of 42-inch corrugated metal pipe and 77 feet of 18-inch CMP to be rehabilitated using cured-in-place lining or cast/structural concrete lining. The city solicited bids from pre-qualified contractors and received three responses; staff recommended Utility Asset Management as the low bidder and presented a contingency that brought the total authorization to $97,245.
Council members asked about specific lining materials and techniques. Mr. Watson described cure-in-place lining and spray/structural concrete approaches and said the choice is driven by site conditions and constructability. Council Member Christopher Zack and others asked about AR glass/chop fiber products; staff said those materials were unlikely for this project. After discussion, the committee approved the task order unanimously.
Staff will execute the task order under the stormwater utility program and return for any contract amendments if contingencies are exceeded.