Summary

Council approved plans and construction estimates or contract awards for street, stormwater, sewer, and pumping-station projects and awarded a $178,120 concrete banding contract; roll-call votes on these items were unanimous.

At its May 4 meeting, the Dubuque City Council approved several public-works projects and awarded a contract for concrete banding and crack sealing, together representing approximately $2.54 million in construction estimates and contract value.

Highlights and outcomes:

- Asbury, Carter & Chaney Traffic Signal Improvement Project: City Engineer Gus Psihoyos recommended adoption of plans and a construction estimate of $297,082.25; council approved sending the project to bid and adopting the resolution (6–0).

- Loras Boulevard & Locust Street Storm Sewer Reconstruction: Council approved plans and a construction estimate of $474,640 to replace about 375 feet of failing storm sewer and reconstruct ADA pedestrian ramps (6–0).

- Loras Boulevard Reconstruction and Repairs Project: Assistant Public Works Director Max O’Brien presented a $383,388.50 estimate to reconstruct concrete pavement in advance of RAGBRAI and to address undermined sections; council approved the resolution (6–0).

- 2026 Public Works Asphalt Milling Profile Project: Council approved the plans and construction estimate of $145,869.35 (6–0).

- Terminal Street Pumping Station Rehabilitation: Water and Resource Recovery Center Director Deron Muehring recommended approval of plans and an estimated probable construction cost of $1,061,000; council adopted the resolution (6–0).

- Concrete banding and crack sealing contract: Council awarded the public improvement contract to Eastern Iowa Asphalt Maintenance for $178,120, a bid 22% below the engineer’s estimate of $228,494; council adopted the resolution (6–0).

- Tri-State Modelers lease: Parks Director Matt Kalcevich presented a lease agreement for use of FDR Park; the Parks & Recreation Commission had unanimously approved the lease on March 10, 2026, and council adopted the lease resolution (6–0).

Each item was placed on the consent or public-hearing portions of the agenda, staff presented plans and cost estimates, and no significant public opposition was recorded during the hearings. The votes were unanimous where recorded.

Next steps: Staff will proceed with bidding, contract award processes, and scheduling; awarded contractors will coordinate with city project managers for mobilization and public-notice steps.