Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Board hears construction update for new PK–12 building; change-order for canopies introduced

Board of Education · June 10, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported substantial on-site activity and finish work at the new PK–12 building; the board considered a resolution authorizing a change order for entrance canopies on the Valley View CFAP 2021 project and asked for additional details before final action.

District representatives updated the Board of Education on progress at the new PK–12 building, reporting "around 150 plus men per day on site" and noting that epoxy and vinyl flooring, sinks and kindergarten casework — cubbies and teacher closets — have been delivered and are being installed.

During new business the board considered a resolution authorizing a change order for entrance canopies for the PK–12 portion of the Valley View CFAP 2021 project (Montgomery County). The resolution and accompanying documents were presented to board members; when the chair asked for additional information a presenter began to describe the proposed work and associated costs but the transcript ends before the board recorded a vote on the change order.

Board members asked for clarification and more detail before final approval; the record shows the item was discussed and that supporting documents had been provided to the board in advance.