Board hears Long Meadow roof low bid and approves solar plans for the school
Summary
The board received a roofing-bid update for Long Meadow Elementary (apparent low bid ~$1.4M) and approved final plans and cost estimates to pursue a solar installation project, with staff noting pending state approvals and separate bidding.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
At its May 20 meeting, the Regional School District 15 Board received a facilities update on Long Meadow Elementary School and approved final plans and cost estimates to advance a solar installation at the same building.
Facilities staff (speaker 8) told the board that roofing bids closed May 6 and the apparent low bidder is Superior Roofing with a bid of about $1,400,000; staff said that earlier cost estimates were near $1.9 million and that the next low bid was roughly $1.7 million. Staff explained that the district’s debt-service encumbrance was just under $1.4 million and that, if the low bid is validated, the district could avoid using reserve funds for the roof. Staff also noted the state reimbursement process — described in the meeting as roughly a 50% return for eligible costs — which would materially lower the district’s net exposure.
On a separate item of regular business, the board moved, seconded and approved a resolution authorizing the final plans and cost estimates for a solar installation at Long Meadow Elementary and directing staff to submit required documents for the state process. Staff described the solar package as a separate bid and said the project’s total gross cost was about $750,000; after state adjustments the figure cited in discussion for district exposure was about $350,000. The board approved the resolution by voice vote.
What was decided: the board authorized staff to proceed with final plans and required state submissions for the solar project and heard a roofing update; contract awards and final contractor selections were not completed in the meeting and will follow staff validation of bids and the state process.
Quotes from the meeting included the facilities update on bids and the board’s procedural approval to move the solar project forward. The board’s next regular meeting is scheduled for May 26, when staff will return with required materials and, as needed, further contract actions.