Post Falls awards $1.23M contract for Westwood water main replacement, agrees construction oversight
Summary
Council awarded the Westwood Water Distribution Replacement Phase One contract to the low bidder (approx. $1.23M with contingency) and approved a construction management services agreement; work targets summer 2026 to avoid school impacts and replaces several thousand feet of aging main.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Council approved a recommendation of award for the Westwood Water Distribution Replacement Phase One project and separately approved a construction management services agreement for engineering oversight.
Project manager Jackson Fleshman said Phase One will replace roughly 5,600–5,700 feet of water main and serve about 74 service connections across the Pine Villa subdivision and adjacent streets, with work scheduled for summer months to avoid Ponderosa Elementary traffic. Nine contractors bid; the low responsive bid was about $1.23 million. Staff requested a 10% contingency (bringing the award request to roughly $1.354M) and explained the engineer’s estimate was higher ($2.2M), a difference staff attributed to a competitive bid environment.
Council also approved a construction management services agreement with the city’s consultant (Century West) to provide construction oversight and inspection; that contract plus contingency was about $248,820. Staff noted the pipeline replacement fund will cover project costs and that savings versus the engineer’s estimate would remain in the fund for future pipeline projects. Phase One construction is planned for summer 2026 with community open house and resident notification in advance.
Next steps: city to issue notice of award, finalize contracts, hold a public open house for affected residents, and begin summer construction coordination to minimize neighborhood impacts.