Bond and facilities update: athletic complex progressing, library delayed by DSA directive, preschool playground complete

Fillmore Unified School District Governing Board · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported progress on the Fillmore High athletic complex (Measure G-funded), library/career center nearing completion pending a DSA change order, a finished preschool playground funded by child development funds, and upcoming Middle School HVAC and shade-structure bids funded by Expanded Learning Opportunity Grant funds.

Assistant Superintendent of Business Services Denise Barrington provided the board an April Bond & Facilities update on April 21, reporting progress across multiple Measure G-funded projects and other site improvements.

Barrington said AMG & Associates is the contractor of record for the Fillmore High athletic complex, with the main gym block walls completed and structural work progressing; the current change in contract price was described as just over $283,000 (about a 1% change) and the project’s estimated completion remains February 2027. She noted the library portion of a library/career center project is substantially complete but the career center is delayed pending a DSA change-order directive relating to a T-bar ceiling; work will resume once DSA issues the directive and the team anticipates completion by mid-May for that project once cleared.

A preschool at San Cayetano Elementary (San Kai Tunnel in the transcript) received a fast-tracked playground funded by Child Development funds; Barrington said wrought-iron fencing, play surfacing and equipment are installed and preschoolers are already using the space. Barrington also previewed summer work: Fillmore Middle School gym HVAC and state shade structure projects now have DSA approval and a May 1 bid opening; Moore Middle School exterior painting is in solicitation and the Fillmore High kitchen/cafeteria modernization is in final design with an anticipated DSA submission in approximately one month.

Trustees asked for confirmation about DSA sign-offs and the status of remaining uncertified projects; staff said only a few projects remain uncertified and that efforts are underway to close them. Trustees thanked the bond manager and project staff for progress on long-running projects and encouraged continued attention to timely permitting and contracting.

Barrington also noted a recently awarded project to Coast Construction for equipment upgrades at two elementary sites funded by the Child Nutrition Fund (amount quoted as $449,000) and design work to transition stadium restrooms to city sewer with the city of Fillmore’s cooperation.