Board approves budget amendments, Kingsboro booster station grant top‑up and several property conveyances
Summary
Edgecombe commissioners approved 10 budget amendments (including health and public works items), accepted EDPNC funding to fill a $2.64 million shortfall for the Kingsboro booster station, and approved conveyances of the county's interest in the Tarboro farmers market and ~3.12 acres to EMC for substation expansion; JCPC and Edgecombe Works program agreements were also approved.
Get email alerts on the Local Fiscal Governance topic
No spam. Unsubscribe anytime.
The board approved ten budget amendments that appropriate additional grants and make transfers across departments, including public health, veterans services, solid waste, and industrial incentive payments tied to past economic development agreements.
On infrastructure, staff reported the low bid for the Kingsboro booster station replacement was $4,493,000, leaving a shortfall after a prior NCDEQ Viable Utilities Fund award of $2,482,800. After applying to the Economic Development Partnership of North Carolina (EDPNC) Mega Site Readiness Program, the county received an additional $2,637,850 to cover the gap; the board approved the grant agreement and corresponding ordinance amendment.
The board also approved conveying the county’s ownership interest in the farmers market building at 507 Albemarle Avenue to the Town of Tarboro, which has been the primary user and will continue stewardship. Separately, the board approved conveying approximately 3.12 acres adjacent to the Kingsboro substation to Edgecombe‑Martin County EMC to accommodate EMC’s planned improvements to support economic development.
Other approvals included JCPC juvenile‑services funding for FY27 totaling $255,122 (with a $25,512 local match) and authorization to execute agreements with recommended programs, a memorandum of agreement with Edgecombe Community College for Edgecombe Works workforce programs (Commissioner Harris recused), and several contracts including a utilities contract and a sole‑source IT backup agreement.