Monomoy plans middle‑school siding work and seeks $11.8 million roof replacement; state reimbursement expected to cover roughly one‑third
Summary
Superintendent told the committee the middle‑school siding project starts March 30; a proposed full roof replacement was estimated at $11.8 million with MSBA reimbursement cited at 37% but a blended reimbursement expected near 33% after exclusions, leaving about $7 million to borrow that would be split between the towns.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Monomoy’s superintendent told the school committee on March 12 that the middle‑school siding project will begin March 30 and that the district plans to seek town approval this year for a full roof replacement estimated at $11.8 million.
The superintendent said contractors will erect fences and staging and will focus initial work on the back side of the fifth‑grade wing and high, exterior siding. He advised the committee that snow days this winter compressed the planned construction window and could affect the contractor’s schedule.
On the proposed roof replacement, administrators and the architects reported an $11.8 million total project and said the Massachusetts School Building Authority (MSBA) initially indicated reimbursement of roughly 37% for eligible portions. The district learned MSBA will not reimburse a portion of the roof that is considered too new, producing a blended reimbursement nearer 33% for the full proposed scope; the superintendent said that would leave approximately $7 million to be borrowed by the district, a cost that would later be split between Chatham and Harwich under the regional agreement.
"It shouldn't be raining in a classroom," the superintendent said while explaining the urgency of replacing aging roofing and reinforcing the district’s case for submitting the full project to town meetings with MSBA reimbursement included.
Next steps are to begin the siding work, document underlying conditions as contractors open siding and to present the roof warrant at town meetings with supporting documentation and videos for voters’ review.