Summary

Consultants for Haines Borough outlined three conceptual designs and a design‑build process for the Lutak Dock replacement at a town hall, while residents urged swift action, highlighted safety and contamination worries, and pressed for budget limits and tenant‑driven operations.

Haines Borough hosted a town‑hall meeting on the Lutak Dock replacement where consulting engineers presented three conceptual designs and an engagement plan and residents voiced urgent concerns about safety, contamination, budget and future operations.

Consultant Paul Wallis, a registered structural engineer leading the technical presentation, told the meeting the borough has defined three required project outcomes: preserve operational continuity for existing freight and fuel operations during construction, retain existing amenities such as compressor buildings and restrooms, and ensure all project plans and specifications remain the property of Haines Borough. "We're gonna design for seismic as required by the code," Wallis said, adding the design will be "right‑sized" for the facility and will not be overdesigned.

Why it matters: Lutak Dock handles essential fuel and freight deliveries for the community; residents and tenants warned that interruptions or insufficient repairs could threaten food and fuel access and public safety. Several speakers said the dock is at or near the end of its expected life and urged timely action within the borough's budget constraints.

Residents and local operators offered sharply different views on how to rebuild the dock. Kimberly Rosado, who identified herself during public comment, described the situation as an emergency: "Human life safety issue, it's a survival for our community issue," she said, citing weeks without freight and shortages of fresh produce. Other residents urged limiting the use of expensive steel and prioritized low‑maintenance rock solutions.

Consultants presented three concepts: (1) a pile/combi‑wall bulkhead 'encapsulation' that would leave much of the existing dock in place, (2) a riprap slope with a partial bulkhead, trestles and dolphins to support barges, and (3) a simpler riprap slope with a single trestle and dolphins described as a more spartan option. Paul Wallis said the preferred vessel for design will be the vessels currently using the dock — a borough assembly requirement — and that the consultants will prepare multiple alternatives and bridging documents to take to a design‑build solicitation.

Budget and scope: Multiple speakers anchored expectations to an approximate $20,000,000 budget. One attendee explicitly urged a design that "meets our current budget of approximately $20,000,000," and consultants repeatedly said they will work to keep alternatives within the funding available from MARAD and any local match the borough chooses to provide.

Contamination and environmental concerns surfaced repeatedly. Residents urged testing and, if necessary, removal of contaminated soil under the existing dock; Don Turner Jr. warned that demolition could uncover pollution from decades of petroleum handling. Nicholas (surname in transcript) argued the industry term "encapsulation" can be misleading because a sheet‑pile wall is not watertight and would not prevent contaminants from leaching. Fred Gray, a former Delta Western terminal manager, responded that spills are reported and remediated under existing regulations but cautioned that riprap could force fuel transfer equipment to be placed over water rather than land, with different spill‑response implications.

Operations and tenants: Consultants reported recent discussions with primary tenants AML and Delta Western and said those operators indicated a reconstructed facility matching the current layout would likely meet their needs. Sean McFarlane, the consultant leading public involvement, told the meeting the team has invited the three grocery‑store owners and the local tribal governments for focused stakeholder meetings and that one tribe has opted to coordinate government‑to‑government with MARAD. "We're going to continuously have in mind the budget that the Haines Borough establishes for that project," McFarlane said.

Permitting, geotechnical work and next steps: The consulting team said it has engaged Solstice (environmental/permitting consultant) and plans to bring on Shannon & Wilson for geotechnical work. The consultants described a series of follow‑up public and stakeholder meetings to develop bridging documents, and they stressed that final scope, budget and design vessel parameters will be set by the borough assembly before any solicitation goes to market.

What was not decided: The town hall was an intake meeting for public comment and did not result in a formal vote or selection of a preferred design. Consultants said their current contract with the borough extends through selection of a design‑build team and that construction‑phase owner's‑representative work would likely be procured separately.

Next steps: Consultants will synthesize public and stakeholder input into bridging documents and return with alternatives and a recommended preferred alternative before the borough issues a design‑build solicitation; tribal and tenant concerns will be addressed through targeted follow‑up meetings.