Council requires written local-hire and procurement plan before approving Central Library construction GMP
Summary
After a lengthy presentation of a phase‑2 guaranteed maximum price and outreach plans from PCL, the council directed staff to return in two weeks with a written local‑hire and local‑procurement implementation plan before approving the contract amendment.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City staff and the construction manager (PCL) briefed the council on the Central Library seismic retrofit and renovation (phase 1 completed; phase 1A selective demolition underway) and presented a proposed phase‑2 Guaranteed Maximum Price (GMP) amendment to PCL.
PCL summarized outreach and economic‑impact planning and said it forecasts about 11–12% local economic impact for phase 2 (local trade partners, suppliers and workforce). Staff presented the amendment amount that would increase the CMAR contract to a total in the high‑hundreds of millions as shown in the agenda materials; the precise figures were included in staff’s report.
Councilmembers pressed staff and PCL for a written, enforceable local‑hire and local‑procurement plan with measurable outcomes and asked for regular reporting. Several members and public speakers said outreach alone is insufficient and asked that commitments be written into the contract or otherwise enforceable. PCL staff described outreach events, a construction opportunity form, and partnerships with Pasadena City College and local workforce programs; they reported phase‑1 local spend of roughly 7% and forecast 11–12% for phase 2 based on market analysis and bid plans.
After debate about schedule risk and accountability, the council voted 6–2 to direct the city manager and PCL to return in two weeks with a written local‑hire and local‑procurement implementation plan; staff will not issue the notice to proceed for phase 2 until that plan is reviewed by the council as directed. Councilmembers said their action was intended to keep the project on an overall schedule while requiring specific, documented commitments on local participation.
Staff and PCL were asked to include specific implementation steps, a timeline, numbers for expected Pasadena residents hired in each trade or job category, a plan for monitoring and reporting, and a recommendation on any additional city staff resources needed to track outcomes.