El‑Sisi business continuity staff outlined planned transmission and substation projects, distribution automation, pole-replacement strategy and vulnerabilities learned after Hurricanes Ian and Milton; council discussed coordination with FPL, underground versus overhead tradeoffs and capital/reimbursement models.

Alan Ruth, Director of Business Continuity at the regional utility, presented a multi-year set of transmission and distribution projects intended to increase capacity and resilience in the Cape Coral service area. Ruth described new substations (including the Kismet project and a northwest substation), conductor upgrades and additional distribution circuits to create looped feeds and reduce the number of customers affected by a single outage.

Ruth described smart-grid investments — distribution automated switches and sectionalizing — that limit outage footprints: "When a fault comes on the system...we're able to see where that outage comes in or reroute that outage so that you can pick up maybe 1,500 or 2,000 members and minimize the outage down to 500 customers or less," he told council. He also explained pole replacement programs (wood, concrete and metal options), targeted vegetation management and pole‑replacement cadence.

Ruth reviewed storm damage photos from Hurricane Ian and Milton showing overhead pole failures and underground pad-mounted equipment and urged cautious evaluation of undergrounding near storm‑surge zones because submerged underground equipment can require lengthy replacement. He said the co‑op purchases bulk power (FPL) and typically secures FEMA reimbursement for eligible restoration costs; as a not‑for‑profit cooperative, the utility does not earn a rate of return like IOUs.

Council members asked about coordination with FPL as a source-power provider, long‑term capital planning and implications of growth in the north Cape corridors; Ruth said the utility maintains a 10‑year plan and is expanding transmission and distribution capacity in growth corridors. No council action was taken; the presentation provided technical context for city resilience planning.