Summary

Road and Bridge Superintendent Rusty briefed the board on spring work, upcoming multi‑week closures on Engineer and Placer roads, drainage repairs and snowshed hazards. Commissioners and emergency managers discussed a town‑county proposal to share a mobile 100‑kW generator and pumps for firefighting and emergency power, with rough vendor quotes and possible 50/50 cost sharing.

San Juan County’s road and bridge priorities, equipment needs and emergency‑power options were a major part of the April 8 meeting.

Superintendent Rusty reported that spring openings and seasonal maintenance are under way. He described planned closures to complete drainage and switchback repairs — work that will require coordinated blocks of time so the popular routes are not repeatedly closed. Rusty said crews will focus this summer on Engineer, Peekune and Placer roads and cautioned that some sections remain mud pits until the grade stabilizes. He also noted a partially collapsed snowshed on County Road 2 that will require assessment and potentially removal for public safety.

Commissioners and Rusty discussed culvert collapses, beaver‑pond impacts to road foundations, grader maintenance (replacement shims for two graders) and the logistics of multi‑jurisdictional work to limit closures.

Separately, resident John Zarcus proposed a shared mobile 100‑kW generator on a trailer and submersible pumps for firefighting, water movement and emergency power for town and county facilities. He presented vendor quotes — new generator prices in the $82,000–$90,000 range and used options with high hours at much lower prices — and a $12,000 range quote for a high‑capacity submersible pump. Zarcus and emergency management staff discussed grant possibilities (including emergency‑management funds), possible Forest Service or federal cost‑shares, storage and maintenance responsibilities, hourly rental rates and intergovernmental agreements to govern priorities during emergencies.

Emergency management staff warned the group that federal wildland response teams are undergoing reorganization and that federal partners may be less predictable in availability, increasing the value of local, pre‑positioned resources. Commissioners signaled they were open to exploring a joint town/county purchase and suggested a 50/50 cost split as a starting point; staff said additional specification work, vendor negotiation and a funding plan would be needed before the board considered committing funds.

The chair asked staff to continue discussions with the town and emergency managers, identify grant opportunities, and draft an intergovernmental agreement that spells out storage, maintenance, priorities of use and liability/waiver terms for private use if leasing is contemplated.

No formal purchasing action was taken at the meeting.