The board gave preliminary approval to Cascade Meadows, a re‑scoped plan for 72 townhome units where a 170‑unit master plan previously existed, subject to staff conditions. Commissioners required further work on affordable‑housing in‑lieu fees, school impact payments and wetlands and utility assurances.

San Juan County commissioners voted April 8 to grant preliminary approval to the Cascade Meadows subdivision, a revised plan that reduces a previously approved 170‑unit master plan to 72 townhome units.

Planning staff told the board the applicant submitted geotechnical and wetlands reports, had started coordination with the U.S. Army Corps on permitting, and provided a letter from the local utility indicating capacity for water and sewer service. Planning staff said the planning commission recommended approval with conditions after debate over affordable‑housing in‑lieu fees and payment to the local school district for impact mitigation.

Planner Willie Tuki summarized staff concerns and conditions: a wetlands permitting and mitigation plan that complies with Corps requirements, a stormwater plan that avoids direct runoff into retained wetlands, geotechnical rock‑fall and debris‑flow mitigation measures, wildfire‑resiliency compliance, and confirmation of utility capacity. Tuki recommended that the board require payment or on‑site provision of units to meet the county’s 10% affordability standard, but allowed the applicant to request a fee in lieu of units.

Staff and the county housing authority provided an affordability gap estimate: roughly $165,600 per two‑bedroom unit; staff translated that into a suggested in‑lieu charge around $16,100 per market‑rate unit that the commission could collect at the time of permit. The Durango fair‑share manual offers an alternative methodology that yields a different per‑unit number; commissioners asked staff to refine and document the recommended formula and CPI indexing approach before final approval.

Applicant agent Lauren Davis (Reynolds Ash) told the board the team had reduced density, planned landscaping and debris fencing, and would follow the county’s recently adopted wildfire‑resiliency code. "We are scaling back and trying to consolidate footprints and be mindful of wetlands," she said, and added the applicant was willing to work with county staff on an appropriate in‑lieu fee schedule.

Several Cascade Village residents urged commissioners to protect neighborhood roads and preserve wetland features. They asked that construction traffic be routed to legal easements on the property’s southern edge rather than through Cascade Village private roads, and raised questions about sewer sizing and the long‑term maintenance of shared infrastructure.

The board’s approval is preliminary and conditioned on: documented wetlands mitigation acceptable to federal and state reviewers; a stormwater plan that protects remaining wetlands; final affordable‑housing fee or unit agreement (including CPI indexing for long phasing); agreed school‑impact payment or dedication as required; utility capacity confirmation to the county’s satisfaction; and bonds or financial assurances for required improvements.