Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Contracts topic

No spam. Unsubscribe anytime.

Board approves change order for OLV Terminal Drive utility work; net cost reported as zero

Olive Branch Board of Aldermen · March 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved change order #1 with Enscore LLC for OLV Terminal Drive utility work after staff reported a pipe‑size discrepancy; the contract adjustment was described as $31,800 but netted to zero after offsets, and no added time was required.

The Olive Branch Board of Aldermen approved change order #1 to the contract with Enscore LLC for work on the OLV Terminal Drive utility project at its March 17 meeting.

Staff reported that field investigation found a 10‑inch sewer pipe where an 8‑inch pipe had been expected, prompting scope changes. Staff told the board that some areas of work were reduced while others increased, and that the net effect of the change order was zero dollars and no change to the project schedule. Staff described the change order amount as $31,800 but said offsets reduced the net fiscal effect to zero.

Board members voted to approve the change order by voice vote. Staff listed the amount during the presentation but said the net change to the contract price was zero after project adjustments.

The board did not require further action; staff will proceed under the amended scope as described.