Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Board approves MHS Performing Arts Center change orders for fire pump, electrical feed and tech upgrades

Milpitas Unified School District Board of Education · October 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved two change orders to add a separate electrical feed and fire pump (per PG&E/fire-life safety) and to add tech/data upgrades; staff said one line item was negotiated down about $25,000 and the net additions are being covered from contingency, which stands near 7.5%.

Milpitas Unified trustees approved two change orders (Nos. 13 and 14) for the Milpitas High School Performing Arts Center at a regular board meeting.

District project staff explained the change orders: one authorizes a separate electrical service and panel plus a fire pump to provide required water pressure to the high stage area, a change driven by fire-life safety and utility requirements; the other covers technology and data upgrades that were recommended after construction began. Project staff said the electrical feed required fire-rated wiring and that the prime subcontractor had delayed submitting costs; the district negotiated the electrical costs down by roughly $25,000.

Board members asked whether the change orders would affect the project timeline or contingency. Staff replied that the change orders add cost but do not change the January target ribbon-cutting; contingency for the project stands at about 7.5 percent of the project budget. One board member asked for a post-completion report outlining challenges and lessons learned.

The board approved both change orders by unanimous voice vote with no abstentions noted in the room.