Fraser council approves sewer lining and pavement-marking contracts, totaling several hundred thousand dollars in authorizations
Summary
Council awarded a $296,720 contract to DVM Utilities for the 2026 sewer-lining project with an approximately $29,000 contingency and authorized AEW construction services; it also approved a three-year pavement-marking contract to PK Contracting (first-year amount $38,337.50).
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
The Fraser City Council on March 12 approved two infrastructure contracts: a sewer-lining construction contract and a three-year pavement-marking contract.
Sewer lining: City staff said the 2026 sewer-lining project will rehabilitate about 6,000 feet of sanitary sewer using cured-in-place liner. Mr. Barrett, a city project presenter, told the council the city had budgeted $500,000 for the project and that DVM Utilities was the low bidder at $296,720. Staff recommended establishing a construction contingency of about $29,000 and authorizing AEW to provide construction-phase engineering services estimated at $44,500. Council moved and approved the recommended award and authorizations.
Pavement marking: For the fiscal-year 2026–28 pavement-marking program, staff recommended awarding a three‑year contract to PK Contracting. The vendor’s first-year price is $38,337.50; the city had budgeted $40,000 for the year. Staff said AEW would provide contract administration; initial administrative estimates of $5,000 were revised down to about $1,500 per year after review. Council approved the contract award and contract-administration authorizations.
What the council approved: Motions at the meeting authorized the city manager and DPW superintendent to execute the sewer contract with a stated construction contingency and to direct AEW to provide construction administration for both the sewer and pavement projects. Council members asked for street-level details (a list of specific streets and maps) on the sewer project, and staff agreed to provide maps showing exactly where lining work will occur.
Votes and next steps: Each motion passed on voice vote at the meeting; staff will present contract documents and construction schedules and will coordinate public notices and street-level lists for affected residents prior to construction.