Fraser council approves sewer lining and pavement-marking contracts, totaling several hundred thousand dollars in authorizations

City of Fraser City Council · March 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council awarded a $296,720 contract to DVM Utilities for the 2026 sewer-lining project with an approximately $29,000 contingency and authorized AEW construction services; it also approved a three-year pavement-marking contract to PK Contracting (first-year amount $38,337.50).

The Fraser City Council on March 12 approved two infrastructure contracts: a sewer-lining construction contract and a three-year pavement-marking contract.

Sewer lining: City staff said the 2026 sewer-lining project will rehabilitate about 6,000 feet of sanitary sewer using cured-in-place liner. Mr. Barrett, a city project presenter, told the council the city had budgeted $500,000 for the project and that DVM Utilities was the low bidder at $296,720. Staff recommended establishing a construction contingency of about $29,000 and authorizing AEW to provide construction-phase engineering services estimated at $44,500. Council moved and approved the recommended award and authorizations.

Pavement marking: For the fiscal-year 2026–28 pavement-marking program, staff recommended awarding a three‑year contract to PK Contracting. The vendor’s first-year price is $38,337.50; the city had budgeted $40,000 for the year. Staff said AEW would provide contract administration; initial administrative estimates of $5,000 were revised down to about $1,500 per year after review. Council approved the contract award and contract-administration authorizations.

What the council approved: Motions at the meeting authorized the city manager and DPW superintendent to execute the sewer contract with a stated construction contingency and to direct AEW to provide construction administration for both the sewer and pavement projects. Council members asked for street-level details (a list of specific streets and maps) on the sewer project, and staff agreed to provide maps showing exactly where lining work will occur.

Votes and next steps: Each motion passed on voice vote at the meeting; staff will present contract documents and construction schedules and will coordinate public notices and street-level lists for affected residents prior to construction.