Summary

Operations staff said utilities are projected to be reduced by $148,000 due to HVAC and LED upgrades; the district plans to remove its last underground 10,000‑gallon oil tank this summer after receiving a favorable bid to be awarded at the meeting. A cloud‑based security and access‑control migration is also budgeted.

Pleasantville officials said planned facility improvements and efficiency measures will lower utility costs even as other maintenance and contractual lines need funding.

Operations presenter Mr. Chamberlain told the board the district is proposing a $148,000 reduction in the utilities budget for 2026–27, citing a more efficient middle‑school heat‑pump HVAC system, near‑complete LED lighting conversion, and a favorable natural‑gas contract obtained through a vendor. "We are lowering our utilities budget by $148,000," Chamberlain said.

Capital and health‑safety actions: Chamberlain and business staff said the district will remove its last underground fuel‑oil tank — a 10,000‑gallon tank behind the high school — this summer. Officials said they received a favorable bid for removal that is being awarded at the board meeting; staff noted that the district experienced a leak from a prior tank in 2007 that required roughly $300,000 in cleanup and ongoing groundwater monitoring. The meeting record does not include a formal roll‑call vote count for the award; the transcript indicates the bid was received and will be awarded as part of meeting business.

Security upgrade: the district proposed transitioning from on‑site server video and door‑access systems to a unified cloud‑based platform that includes ten‑year hardware warranty and five years of software subscription; the work is planned as a capital project with implementation, cloud connectors and hardware budgeted for this summer.

What this means: officials said the combined efficiency work and modernization (BMS upgrades across three buildings, LED lighting, HVAC fine‑tuning) reduce the district’s near‑term utility exposure while capital projects and security upgrades will require interfund transfers and ongoing maintenance contracts. The removal of the underground oil tank is described as a reduction in long‑term environmental and insurance liability.

Next steps: the oil‑tank removal contract is slated for award at the board meeting and the BMS/security projects are planned for this summer through vendors on state contract; project funding is included in the proposed budget and capital interfund transfers.