Alpena approves $430,916 in odor‑control upgrades at water recycling plant
Summary
City engineers presented sole-source proposals to replace end-of-life components and add SCADA integration for the plant's odor-control system; council authorized purchase orders covering a total cost of $430,916.18 to Evocal Water Technologies (original installer) and Tempest Enterprises (SCADA contractor).
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City Engineer Steve Schultz told the council that the odor‑control system installed in 2001 requires replacement of electronic components, pumps and piping, plus integration into the city's SCADA system. Staff obtained quotes from the original system installer (Evocal Water Technologies) and from the SCADA contractor (Tempest Enterprises LLC), which were described as sole‑source for compatibility reasons.
The engineer reported a combined total proposal cost of $430,916.18. Council authorized two motions to accept the proposals and to issue purchase orders to the two contractors so the upgrade and integration work can proceed.
Staff said $390,000 was already budgeted for odor control improvements and that savings from prior projects in the capital outlay line would cover the remainder. Implementation will include standardizing piping so in‑house crews can perform future maintenance, and adding monitoring/control capabilities to the SCADA system.
Next steps: staff will issue purchase orders and schedule the work; project oversight will remain with the city engineer's office.