Stark County approves $94,705 payment to Toews Construction for livestock building
Summary
The Stark County Park Board approved payment No. 7 of $94,705.90 to Toews Construction for work on the new livestock building; contractor reported final concrete and electrical work remain and expects completion around May 15, weather permitting.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Stark County Park Board on a roll-call vote approved payment No. 7 of $94,705.90 from the special project fund to Toews Construction for work on the county’s new livestock building.
Mr. Toews, the contractor on site, told the board the remaining tasks are pouring the cattle pad and completing sewer and electrical hookups. "We anticipate being done by about May 15th," he said, adding that crews are waiting for frost to leave the ground so electricians can finish outside work.
Board members who spoke during the item praised progress and the road department’s work on site. The motion to approve the payment was seconded and passed with a unanimous roll-call vote.
The payment covers construction pay application No. 7; the board conducted a brief review of the project schedule and asked county staff to track final invoices and confirm the electrical completion date. No further conditions were attached to the payment approval.
Next steps: staff will monitor the contractor’s completion timetable and include final acceptance paperwork on a future agenda once punch-list items and utilities are finished.