Summary

Clive council closed a public hearing, received six bids for the 114th Street Bridge repair and awarded the contract to Boulder Contracting after council review and roll-call votes.

After a published public hearing, city staff presented bid tabulations for the 114th Street Bridge repair on April 10. The council heard that five of the six bids were below the engineer’s estimate and that staff recommended awarding the contract to Boulder Contracting based on the bid tabulation and the design engineer’s comfort with Boulder’s track record.

The council closed the hearing, accepted the bids and approved a resolution awarding the contract by a recorded vote. The clerk’s voting record shows the motions and award passed by a vote of five-to-zero.

Staff noted a substantial completion target in mid-June to align with the existing street closure, and council members had no public comments in chambers opposing the award. The meeting packet contained a tabulation of the six bids, and staff said they would be available to answer follow-up questions about procurement and construction schedule.