Summary

County staff reported contractors completed flooring and painting on the Alba senior citizens project; hood suppression equipment was expected that week, but ductwork did not meet code and requires supports before a final inspection targeted for the 24th.

Staff updated members on the Alba senior citizens project during the March 9, 2026 meeting, saying most interior finishes are complete and contractors expected to finish hood suppression installation in the coming week.

According to the update, the ductwork coming off the main unit did not meet code and requires additional support pieces and other corrections before the fire-suppression system can pass inspection. Staff said flooring and paint are finished and that contractors were aiming for a final inspection on the 24th.

Why it matters: The corrections — support pieces for ductwork and proper installation of the suppression hood — are required for the project to meet code and open for occupant use. The timeline for final inspection affects when the Alba senior facility can be fully commissioned and serve residents.

What happens next: Staff will monitor contractor completion of the hood suppression installation and the ductwork corrections; the meeting record lists a target of the 24th for final inspection.