City outlines $1 million capital-outlay grant, plans for wastewater plant upgrades

Truth or Consequences City Commission · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff described how a $1 million New Mexico capital outlay grant will be applied to wastewater treatment plant upgrades (including $10,000 earmarked for art in public places), explained the project will target 51 deteriorated pits and a problematic Hagen Street line, and asked commissioners to authorize related resolutions and the grant agreement.

City staff told the commission the city had received a $1 million New Mexico capital outlay grant for wastewater treatment plant upgrades and asked the commission to authorize the related resolution and execute the grant agreement.

City manager Alvarez said $10,000 of the grant is allocated to art in public places and that staff hopes to use part of the upgraded facility as a public gallery space. Alvarez said the $1 million is part of a broader plan that began with a $4 million request to the governor as part of a roughly $5 million improvement strategy.

Tracy and other staff described the immediate engineering priorities: rebuilding 51 sewer pits that currently lack proper inflow protection and replacing a failing upper-line on Hagen Street that the crew and engineer believe is a primary cause of downstream system failures. Tracy said staff expects to move quickly to request-for-proposals (RFPs) or a cooperative contract once final documents are prepared.

Staff explained some earlier 2018 design work used fiberglass where stainless steel was specified; the new funding will allow the city to correct those deficiencies as part of initial engineering. The city indicated it also expects to seek additional funding (including possible water-trust-board or other grant requests) to complete remaining phases.

The commission approved the resolution authorizing the project and later authorized execution of the capital outlay grant agreement itself as a separate action. Staff said, if all funding falls into place, the upgrades could reduce or eliminate some planned future rate increases.

What’s next: staff will finalize grant paperwork, complete engineering plans and issue procurement documents for the initial phase (rebuilding pits and addressing the Hagen Street line).