Weld County authorizes temporary closures of County Roads 59 and 13 for milling and paving

Weld County Board of County Commissioners · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved full closures of County Road 59 (March 23–May 8) and County Road 13 (March 23–June 9) to allow milling, paving and railroad‑grade work. Detours are paved and variable message boards will be posted, Public Works said.

The Weld County Board of Commissioners on March 9 approved temporary full closures for two county roads to allow milling and paving work.

Amy Muty of Public Works asked the board to close County Road 59 between County Roads 74 and 78 from March 23 through May 8 for a full mill and paving project. Muty said the road currently has a recycled‑asphalt surface and that the work will include milling, blading and paving; detour routes within the closure are paved and will be dust‑treated, and variable message boards will be placed in advance and during construction. Commissioner Ross moved to approve the closure; Commissioner Buck seconded the motion, which was recorded as carried unanimously.

Public Works also requested closure of County Road 13 beginning March 23 through June 9 for a full paving project that includes milling and work at a railroad grade to smooth the transition. Muty said the detour routes for this closure are paved and will have variable message boards posted. Commissioner Maxi moved and Commissioner Buck seconded approval; the motion carried unanimously.

The transcript records a minor inconsistency in the endpoints cited for County Road 13: the presentation described the closure as between County Roads 74 and 68.5, while the recorded motion referred to County Roads 74 and 16. That discrepancy was not resolved on the record; Public Works staff will finalize construction notices with exact limits prior to the March 23 start date.

No public comments were offered during the meeting about the road projects. The board did not attach special conditions to the approvals beyond the construction‑period dates and standard detour/dust‑mitigation measures described by Public Works.