City Administrator Sam Sykes told the council several systems are aging: HVAC units at city hall require replacement, the water plant is working hard to control turbidity (risking a boil order), parts for a failing Cicada 5 system were ordered, and sewer clarifier piping needs replacement with an estimated cost under $200,000.

City Administrator Sam Sykes briefed the council on multiple infrastructure items and capital plans.

Sykes said the city will replace five of 27 heat exchangers in city hall after a major air‑handler failed and that parts are being ordered for a failing Cicada 5 component at the water plant. He warned that seasonal runoff is stressing the treatment plant and that "we could go into a boil order which can really affect the dialysis clinic, the hospital, and some of the elderly around us." He described plans to seek NRDP funding for lower‑reservoir work and noted spare‑parts procurement for the water plant.

On sewer infrastructure, Sykes said two sections of 8‑inch piping from the clarifiers to the oxygen discs are failing—decades‑old repairs reduced internal diameters with flex hose that is now leaking—and replacing them could escalate into a much larger job; he estimated keeping repairs under $200,000 in the coming year if managed proactively.

Sykes also described plans to pursue a grant to upsize a building generator so the facility can provide backup dispatch and warming‑center functions during major outages, and previewed near‑term road work (Spruce Street reconstruction) and future bid solicitations.

Why it matters: City officials described operational and public‑health implications (boil‑order risk), near‑term capital needs, and grant opportunities that will influence budgeting and service continuity.

Next steps: Staff will obtain quotes for repairs, pursue grants (NRDP, generator funding), and bring contract approvals or funding requests to the council as projects are refined.