Redevelopment authority approves up to $10,000 for MEPA scoping and hears proposal for Flint neighborhood water line
Summary
Board approved a not-to-exceed $10,000 authorization to hire consultants to define MEPA/NEPA requirements for the Urban Renewal Plan and consider a roughly $10,000 water-line proposal to support a community garden in the Flint neighborhood.
Get email alerts on the Neighborhood Development topic
No spam. Unsubscribe anytime.
The Fall River Redevelopment Authority approved up to $10,000 to engage planning consultants to determine MEPA/NEPA requirements for the authority's Urban Renewal Plan and to develop a scoped work plan under the new regulations.
Staff told the board that MassHousing has funded significant earlier work on the urban renewal and NEPA review but cannot use the remaining $63,000 in a Flint-targeted grant for capital work such as installing a permanent water line to support a community garden. Staff estimated the water-line work could cost about $10,000 and said the park department has approved the project design; the authority’s contribution under the proposal would be installation of the line, not ongoing water service.
Because the next steps for MEPA/NEPA under the new regulations are not fully defined by staff or consultants, the board approved a not-to-exceed $10,000 authorization to increase consultant scope (transcript names referenced as Inis/Land Strategies and Tie and Bond) so consultants can tell the authority what is required and prepare a scope of work and budget for the full MEPA process.
The motion passed unanimously; board members asked staff to return with the consultant scope, cost estimates and follow-up recommendations at a future meeting.