Temple City reports $5.5 million in recent road work; pavement product held up in rain tests
Summary
City manager reported completion of major streets beautification and roughly $5.5 million in recent road work covering arterial and residential streets, noting use of a new surface treatment (AAM) that performed well in recent rains and thanking public-works staff and contractors.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City staff told the council on Dec. 16 that recent infrastructure work and beautification projects in Temple City are nearly complete and that recent pavement work totaled about $5.5 million.
The city manager told the council the Las Tunxis (project referenced as part of the 'Urban Renaissance' feature in the city’s Connect publication) improvements are 99% complete, with blade signs and awnings still moving through an application process. He credited public-works staff and contractors for the finish.
On pavement work, the manager said staff performed approximately “2.6 million square feet of road improvements,” which he described as equivalent to roughly 16 miles of arterial work plus about 15 miles of residential streets, at a reported total cost of about $5.5 million. He said staff used a product called “AAM” (described as a dense, durable surface treatment) in some test sections; following recent heavy rains, field reviews found the material holding up well.
The manager said the city will present an updated pavement-management plan to the council in January to show progress and remaining challenges. He also thanked specific staff and contractors named during the update.
The city did not provide a line-item breakdown of the $5.5 million in the meeting; staff said they will provide a pavement-management update in January with additional details.