Library board approves bundled design services for main‑building renovation, accepts $315,000 proposal
Summary
The Franklin Township Public Library Board of Trustees voted unanimously Dec. 17 to accept Aari Aino Architects' bundled professional‑services proposal for HVAC, roof and interior renovation design work (fee $315,000), a $60,000 savings compared with separate contracts; the board said bundling reduces scheduling conflicts and contractor finger‑pointing.
Get email alerts on the Library Renovation topic
No spam. Unsubscribe anytime.
The Franklin Township Public Library Board of Trustees voted unanimously Dec. 17 to accept a bundled professional‑services proposal from Aari Aino Architects to handle design work for three main‑building projects: HVAC replacement, roof replacement and an extensive interior renovation. The board approved the proposal as presented during the meeting and accepted the firm’s bundled fee of $315,000, which the board said is $60,000 less than the combined fee if the projects were contracted separately.
Board leadership summarized the scope of the architect’s work as including architecture and demolition drawings, interior finishes design (excluding furniture), mechanical, electrical and plumbing engineering, fire‑protection engineering, and third‑party estimating at the end of design phases. The presentation cited line items that the firm estimated separately for the larger effort—about $50,000 for HVAC services and about $75,000 for roof services—while noting the interior renovation estimate is more extensive and was discussed in detail by board leadership and the director.
During discussion, the board considered procurement options and whether to bid each project separately or bundle them under a single general contractor. The board’s president and Director January Adams said they initially had reservations about bundling but were persuaded that a single general contractor would reduce schedule conflicts and responsibility disputes between multiple contractors. A board member moved to accept “option two” (the bundled approach) and another member seconded; after no further discussion the board voted in favor and the motion passed unanimously. The transcript does not record the names of the motion maker or seconder, nor does it record a roll‑call tally.
The board received related correspondence and operational updates during the meeting, including a note about vendor changes in the book‑supply market and the library’s current use of Ingram. The board scheduled no further action in the meeting beyond accepting the professional‑services proposal; the recorded next procedural step is that staff will proceed according to the accepted professional‑services engagement and report back as required.
The board’s motion to accept the proposal concluded the old‑business portion of the meeting. The board will next meet Jan. 28, 2026.