Florence council approves small change order for Well 5 rebuild after startup issue

Town of Florence Town Council · March 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized Change Order No. 4 for the Well 5 rebuild, adding $11,652.72 for piping and reconfiguration after startup problems; town staff said a 10-day contractor-run trial will precede town acceptance.

Public works staff told the council that startup testing for the Well 5 rebuild revealed a missing pump-to-waste valve and an unintended discharge that affected a neighbor. Staff requested approval of Change Order No. 4 to perform pipe reconfiguration and move the injection point, adding $11,652.72 to the contract and increasing the K&G contract to an amount not to exceed approximately $2.6 million.

Jonathan explained that the change order corrects issues observed during initial startup and that town crews will assist with trenching to reduce costs. The contractor will perform a 10-day trial run under contractor oversight; if successful, the town will take ownership of the well and place it into operation.

Council approved the change order without additional conditions.

Why it matters: Restoring Well 5 is an operational priority for the town’s water supply; the change order is small relative to the overall contract but required to correct a functional problem before full startup.

What’s next: The contractor will oversee a 10-day test run; staff will report any issues identified during the trial before final acceptance.