Tequesta utilities present major water and stormwater projects; staff flags PFAS testing and $5.745M SRF loan

Village of Tequesta Village Council · November 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Utilities deputy director Allison Felsburg briefed council on living-shoreline and swale projects, five stormwater pipeline sites, filter-media and RO membrane replacements, a $5.745 million SRF loan for treatment improvements, and tests showing PFAS/PFOS in finished water that will require a master-plan response ahead of 2029/2031 compliance deadlines.

Allison Felsburg, utilities deputy director, delivered a comprehensive utilities update at the Village of Tequesta council workshop covering stormwater, production, distribution and customer-service projects.

On stormwater, staff described a living-shoreline bank stabilization project (presented as 50% grant-funded and shared with the Town of Jupiter), swale reclamation work planned for FY26 and five planned pipe-lining projects totaling about 618 linear feet. Staff said pond inlet/outlet inspections and in-water diver clearing are scheduled for identified locations and that quotes for several projects are under review.

In production, utilities reported ongoing filter-media replacement in aging filter vessels (some original to 1982), and an RO-membrane replacement project with new membranes arriving and contractor mobilization scheduled. Allison told council the village executed an SRF loan agreement on July 1 for $5.745 million to fund water-treatment plant improvements — including conversion from gas to liquid ammonia for disinfection, instrumentation and RO system upgrades — and that the remainder of the project will be funded from reserves.

On contaminants, staff said testing under an unregulated-contaminant monitoring rule identified PFAS/PFOS in finished water above the levels anticipated under future maximum contaminant limits. Allison said the village will present a water-treatment master plan from Kimley Horn at an upcoming meeting to identify both near-term compliance solutions and longer-term options ahead of the 2029/2031 deadlines.

Distribution highlights included coordination with Martin County’s County Line Road bridge project that requires replacement of two village mains, progress on the Water Main 1 to Questa Drive replacement (with short daytime closures planned), and a Beach Road (Water Main 2) phase 2 SRF-funded project scheduled for bidding and mobilization. Staff reported the village owns and maintains about 630 fire hydrants and 1,123 potable-water valves and has contracted third-party hydrant inspections and is instituting valve exercising and dead-end flushing practices.

Allison also said the village’s backflow-prevention compliance is just over 50% and staff plans a council workshop to present recommendations to raise compliance; she noted outreach initiatives (including a school 'Drop Savers' program) to increase public education.

Council thanked staff and asked for additional detail on timelines, potential overlapping construction impacts, and additional data on PFAS mitigation options; staff said they will return with the Kimley Horn master-plan presentation and further procurement timelines.