Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Downtown Revitalization topic

No spam. Unsubscribe anytime.

Commission approves downtown revitalization contract; public raises concerns about shade and access

Mount Clemens City Commission · June 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mount Clemens commissioners awarded a roughly $5.49 million contract for downtown revitalization—including major underground work and a December 20 completion deadline—while public commenters warned the redesign could create a heat-prone, concrete plaza and impede business access.

Mount Clemens City Commission voted to award the downtown revitalization contract to B Construction Inc., authorizing a base bid of about $4.99 million plus a 10% contingency for a total not to exceed approximately $5.49 million.

Administration told the commission that only one bid was received, that the project’s true scope involves extensive underground utilities and specialized excavation, and that the contractor must deliver a functional road and sidewalks by Dec. 20. City staff said the total project, including an adjacent parking lot and contingency, is currently estimated at roughly $6.69 million and that about $6.47 million in funding has been secured; any shortfall—approximately $64,900—would be covered by the city’s general fund if needed.

The city’s lead engineer, Kyle, explained why specialized subcontractors are required for deep excavation and sanitary lead replacements and said the selected contractor committed to the aggressive schedule. Administration also confirmed the work will be subject to prevailing-wage requirements tied to the project’s funding source.

At the public comment period, resident Steve Alter warned that the planned downtown surface treatments and limited greenery could make the plaza a ‘‘hot box’’ in summer, saying, “it's going to be too hot,” and expressed worry about lost shade, impacts to businesses with outdoor patios and parking. Commissioners acknowledged those concerns and said they will continue to work with property owners to maintain access during construction. Staff said they held post-bid meetings with multiple contractors and that capacity constraints among contractors likely limited competition.

The motion to approve the contract carried by voice vote.

The commission set project milestones and emphasized the December deadline for a functional corridor; construction was announced to begin May 28, 2024. Next procedural steps include contractor mobilization and ongoing coordination with downtown businesses and utilities.