Summary
Supervisors awarded the Old Highway 49 overlay bid to AJ Construction and authorized advertising and activation for several road projects and an ERB‑funded bridge replacement; staff said the project is an LPA match and estimated start is weeks to months depending on procurement.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Rankin County Board of Supervisors awarded a low bid for the Old Highway 49 overlay and moved several road projects forward at its March 2 meeting.
County staff presented a certified bid tab and recommended awarding the Old Highway 49 overlay to the low bidder, AJ Construction Inc. The bid amount in the meeting materials appeared as a garbled figure in the transcript (1,626,67041); staff said the low bid was under the engineer’s estimate. The board approved the award. Staff described the project as an LPA (local public agency) project with an approximate 70/30 funding split, with the county matching roughly 30% and a 10% city contribution noted in discussion.
Tim Parker, presenting other agenda items, secured authority to advertise clearing and grubbing for the Florence B Parkway project between Clear Road and Highway 049 and obtained approval to advertise the SAP 6120M overlay project covering five local roads (Florence B Road, Star Brandon Road, Lucky Road, Northshore Parkway and Midway Road). The board also authorized advertising for an Erlich Road bridge replacement (ERB project funded by MDOT) and activated a Transportation Alternatives Program project to create a shared‑use path at Pisgah High School.
Staff projected construction procurement and start windows: award has taken place and the county expects to move to construction procurement and a contractor within several weeks to months, with some projects estimated to advertise and reach contractor selection in about 60 days.
Because the transcript captured a malformed numeric string for the Old Highway 49 low bid, the reported dollar figure in the minutes was not fully legible in the recording; staff and official bid documents should be consulted for the precise award amount.