Kokomo City board approves fire‑station pay apps, extends crack‑seal contract

Board of Public Works and Safety · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Kokomo City Board of Public Works and Safety approved two pay applications for ongoing fire station reconstruction, took mowing bids under advisement, authorized nuisance cleanups on two properties and approved a contract extension for the city's crack‑seal program not to exceed $149,999.

The Kokomo City Board of Public Works and Safety on March 11 approved routine construction payments and a contract extension, and authorized crews to enter two properties for nuisance cleanups.

The board approved pay application number six for the fire station reconstruction, awarding $520,823.25 for completed work — including apparatus wall construction, structural steel erection, perforated panel delivery, foundation insulation and waterline insulation — and directed that $27,411.75 be placed in an escrow retainage account. A board member moved to approve the application and the motion carried.

The board also approved pay application number seven for the same fire station project, in the amount of $342,595.65 for work completed to date (slab on deck, CMU walls, structural steel, wood blocking, insulation and underground plumbing) and $18,043.35 for retainage.

The board received several bids for the city’s 2026 mowing contract — named bidders included JNA Hartman Farms LLC, Sunshine Mowing and Landscape, Oakide Land Solutions LLC, Maynard’s Mowing and Agreeable Lawn Care — and voted to take the bids under advisement for further review rather than awarding the contract at the meeting.

On nuisance properties, staff member Chelsea reported that listed properties remain in violation and requested permission for city crews to enter and remove abated items at 103 North Bell Street and 1210 North Webster Street. The board approved the request by motion.

Clint Benadder, superintendent of the Public Maintenance and Refuge Department, recommended a contract extension with Pavement Solutions Incorporated for the 2026 crack‑seal season at $130 per pound, not to exceed $149,999, saying the work could not be completed in 2025 because of excessive rain. The board approved the extension.

The board then approved claims and adjourned. The transcript records the claims motion but does not provide a clear, reproducible total in numeric form; the claims amount is recorded in the meeting transcript as an unclear value and therefore is listed as not specified in this report.