Granbury approves updated $3.415 million cost estimate for US Highway 377 breakout project
Summary
Council adopted Resolution 26-24 approving updated cost estimates for the US Highway 377 breakout project; the city's share increased by $708,679.92 to a new total of $3,415,088.50, with staff saying funding will come from a TxDOT state infrastructure bank loan.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Granbury City Council on April 21, 2026 voted to adopt Resolution 26-24 approving updated cost estimates for the US Highway 377 breakout project, including a 4% inflation factor and a 10% contingency, which raised the city's portion by $708,679.92 to $3,415,088.50.
Staff said the cost increase reflects materials and inflation adjustments communicated by TxDOT and that the city’s funding will come from a state infrastructure bank loan arranged through TxDOT. Chris Sharp reviewed project photos and explained the city had previously approved aesthetics upgrades for the 377 project; council was told the approval is necessary to keep the project on schedule for an anticipated October letting if utilities and other tasks are coordinated.
A council member asked whether the schedule could be accelerated; staff said they would work to maintain the timetable. Council approved Resolution 26-24 on a voice vote with five ayes and zero nays; one council member was absent. The resolution updates internal cost estimates and keeps the project moving toward TxDOT’s planned schedule.