Post Falls awards Seltice Way reconstruction and utility contract, including pipeline work

Post Falls City Council · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a roughly $5.43 million construction award to MDM Construction Group and a construction‑management services amendment for the Seltice Way rehabilitation and pipeline project; total project cost is estimated at about $7.9 million with Rathdrum and EGID sharing portions via MOUs.

The Post Falls City Council approved contract awards on April 21 for a major Seltice Way reconstruction that combines a full roadway rebuild with extensive wastewater pipeline work.

Public works staff described the project as a full‑depth reconstruction from subgrade to new pavement, intended as a 20‑year design that also installs six different pipelines (including a force main to accommodate future flows). Staff presented memoranda of understanding with the City of Rathdrum and East Green Acres Irrigation District (EGID) to define cost shares and roles; Rathdrum’s proportional share of construction was described as roughly 16 percent, and EGID’s protection and relocation work is estimated under $200,000 and will be reimbursed by the city per the agreement.

Bids opened March 24 produced a low responsive bid from MDM Construction Group at just under $5.0 million. Council approved the construction contract with a 10 percent contingency and a construction‑management services amendment; the total council authorization for the construction award and CMS amendment was roughly $6.78 million on the evening’s motion. Staff said the overall project estimate is approximately $7.9 million, with utilities bearing about 56 percent of the cost, streets about 28 percent, and Rathdrum about 16 percent.

Construction will be phased into four stages to maintain traffic during work; intersections will be closed for certain phases with posted detours and one intersection allowed closed at a time. Staff said they expect the contractor to work through a construction season stretching into the following year and that public outreach will be ongoing about closures and detours.

What happens next: Staff will execute the contract, coordinate construction phasing, publish detour plans and continue outreach; Rathdrum and EGID will reimburse agreed shares per their MOUs.