District 214 trustees flag Kirk project cost jump to $9.5 million and warn of possible assessments
Summary
Superintendent and board members said the Kirk project’s estimate rose from $5 million to $9.5 million, prompting calls for clearer cash‑flow reporting and warning that the district could face future assessments as the NSSEO budget is amended.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Township High School District 214 trustees were told on Oct. 10 that the Kirk project — a facility upgrade for special‑needs programming administered in coordination with NSSEO — has grown from an initial estimate of $5 million to $9.5 million, raising budget, transparency and potential assessment concerns.
Mr. Fito, speaking during the superintendent’s report, said the amended budget for the Kirk project had not been voted on by the NSSEO governing board and will require additional budget amendments at multiple levels. "The KK project was initially estimated at $5 million and now it's up to 9.5," he said, noting the change was "desperately needed" for students housed in those facilities but also stressing the need for better cash‑flow information from NSSEO.
Board members and administration said they will work with NSSEO to obtain a detailed cash‑flow report showing project revenues versus expenses and to tighten the planning process. The presentation referenced Tim Keeley (district finance) as the staff lead who will help produce that information.
The superintendent’s report also noted a concern about a $750,000 commitment referenced at a recent local event, with Mr. Fito saying he "had serious reservations about a $750,000 commitment made by former Senator Gillespie and current Senator Walker" and warning there are "no additional funds for school districts next year" at the state level. He said that, given statewide budget pressures, the district may face future assessments to cover cost increases unless other funding materializes.
Board members emphasized that the district needs a clearer timeline of when additional funds would be required and recommended that administration present a project cash‑flow and funding plan before approving further expenditures tied to the Kirk project. The board did not take an additional vote on the project at the Oct. 10 meeting.
The district also noted other facility pressures in the superintendent’s report, including insurer‑approved mold remediation and associated costs at Timber Ridge Elementary.