District construction update: contingency, $281K slush fund and recommended corridor repairs

East Aurora Union Free School District Board of Education · March 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District construction managers reported unexpected work covered by contingency and presented options to spend a $281,000 leftover balance and part of contingency to finish first-floor corridors, add window shades, upgrade cameras and install a security door; the team recommended prioritizing hallway finishes and preserving contingency for unknowns.

District construction staff briefed trustees on recent developments in the district's capital project and a recommended use of remaining bid-day funds.

After heavy demolition exposed unexpected conditions (including framing repairs in an upper library), the project team said contingency funds have absorbed recent surprises and that about $225,000 remains available in contingency alongside a separate $281,000 balance identified for additional work. Contractors returned pricing for state-approved alternates totaling roughly $420,000. To use available funds prudently while preserving contingency for any further unforeseen issues, the project team recommended prioritizing completion of first-floor corridor finishes (new flooring, ceilings, lighting and paint), purchasing additional window shades, modest camera-system upgrades and a glass door / security separation that would improve access control between the district office wing and public areas.

Project staff emphasized logistics: corridor work is difficult to postpone into the school year and would benefit from summer scheduling, while smaller office renovations could occur later or be isolated to limit disruption. Staff also reminded the board that capital-project expenditures must follow the referendum scope and State Education Department construction numbers; work outside those boundaries would require additional approvals or a new vote.

Next steps: the board discussed the list and asked project staff to proceed with the prioritized corridor work and to return if contingency expenditures approach limits; any further allocation will be recommended only after drywall is back in place and the condition of remaining spaces is fully known.