Board hears facilities update; HVAC replacements for Fisher and Van Meter to use CMAS procurement
Summary
Facilities staff reported that HVAC replacement plans for Fisher and Van Meter are under review by DSA and that the district plans to use the California Multiple Award Schedule (CMAS) to accelerate procurement; estimated construction cost for the HVAC work is about $9 million and DSA application fees were reported around $70,000.
Get email alerts on the Facilities Procurement topic
No spam. Unsubscribe anytime.
District facilities staff updated the board on bond-funded projects and procurement plans, reporting that HVAC replacement plans for Fisher and Van Meter have been submitted to the Division of the State Architect (DSA) and are currently under review.
A staff presenter explained that the plans "went to DSA... so they're currently in review" and that the facilities team is performing constructability reviews while preparing procurement. The district intends to use CMAS (California Multiple Award Schedule) for some procurements to expedite long-lead items and prequalified vendor services, the presenter said: "CMAS is... a program that any state agency can use, schools, counties... It's a process that allows you to procure product that may be long lead."
Board discussion touched on project costs and DSA fees. A staff member noted the district paid approximately $70,000 in DSA application fees for the projects. On project size, staff described the two-school HVAC effort as an estimate of about $9,000,000 in construction costs combined and said CMAS includes several vendors with the same pricing menu so the district can choose local divisions under that schedule.
Questions from trustees focused on whether CMAS would apply to all three planned projects, whether labor as well as hardware was included for specific vendors, and how many CMAS vendors would be available locally; staff responded that some vendors offer both hardware and labor and that multiple CMAS vendors exist nationwide with local divisions.
This item was presented as an informational update and not an action item; staff said procurement and final project reconciliation (including any additional DSA invoices) will occur as projects move toward construction.