Commission recommends approval for small industrial building at 990 St. Charles Street
Summary
The Elgin Planning and Zoning Commission voted 7–0 May 4 to recommend city council approve a conditional planned development for a roughly 2,000 sq ft light-industrial building and four parking spaces at 990 St. Charles Street (Advantage Property Holdings LLC), with conditions including no outdoor storage and agreement not to object to future easements.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Elgin Planning and Zoning Commission on May 4 recommended city council approve Petition 49-25, a conditional planned development to allow a roughly 2,000-square-foot, one-story light-industrial building at 990 St. Charles Street.
City staff told the commission the applicant, Advantage Property Holdings LLC, seeks departures from the Elgin Municipal Code to accommodate the small lot. Staff said the parcel is 10,431 square feet in a Commercial-Industrial (CI) zone and lies at the southwest corner of St. Charles Street (Illinois Route 25) and Hammond Avenue. The proposed building would sit close to St. Charles Street with a four-stall parking lot behind it; staff said the company anticipates four to five employees and that the code’s requirement of 1.5 parking spaces per employee means three spaces are required for five employees, so the four provided meet the requirement.
Staff described two code departures the applicant requests: reduced street setbacks (code requires 25 feet; the proposed building would be about 13 feet from the north property line and roughly 21 feet from the east property line, where an historic right-of-way easement complicates measurements) and reduced vehicle-use-area interior setbacks (parking closest points of about 3–4 feet from adjacent property lines). Staff said those reduced setbacks still allow required perimeter landscaping and recommended approval subject to the conditions included in the packet, including a condition that no outdoor storage be permitted and that the developer not object to future utility easements along the north and east property lines.
Applicant Josh Mullins said the new building would serve the applicant’s property-management business operations and would replace a vacant single-family residence currently on the site. Mullins said the structure is intended to be the company’s own operations facility and that no outdoor storage is planned.
Several commissioners asked technical clarifying questions about parking math and the historic roadway easement along the east property line. Staff clarified the distinction between the easement and the property line, explained how right-of-way and curb/sidewalk locations affect setback measurements, and reaffirmed that four parking stalls satisfy the requirement for the expected staffing level. The public-comment period drew no speakers.
A motion to recommend approval subject to packet conditions passed on a roll-call vote of 7–0. The recommendation will be forwarded to Elgin City Council for final action.
Meeting note: staff presentation and Q&A appear in the record, and staff recommended approval with conditions; no public opposition was recorded.